Hi Bob,

The Format Duration macro (Tools --> Macro--> Macros-->
Format_Duration --> Run) allows you to change the
duration measurement used.

HTH
Julie
 
G

Gérard Ducouret

Hello Bob,
Try to run the format_Duration macro :
Tools / Macros / Macro / Format_Duration / Run...

Gérard Ducouret [Project MVP]