D
David.B.Richter
I am looking for help or examples on writing a project VBA application
that would do the flowing:
I need to take the Resource Time Scaled data from the BaselineWork
fields and copy/move it into the Resource Time Scaled data of the Work
filed. Yes, just the opposite of saving the Baseline function in
project. I have used the "TimeScaleData" Method to get the data from
the BaselineWork filed, but I do not understand how to get those
values into the Work fields. Also I need to do this for ALL resource
in the project from a specific start and end date. Any help or
examples would be great. Thanks Dave Richter
that would do the flowing:
I need to take the Resource Time Scaled data from the BaselineWork
fields and copy/move it into the Resource Time Scaled data of the Work
filed. Yes, just the opposite of saving the Baseline function in
project. I have used the "TimeScaleData" Method to get the data from
the BaselineWork filed, but I do not understand how to get those
values into the Work fields. Also I need to do this for ALL resource
in the project from a specific start and end date. Any help or
examples would be great. Thanks Dave Richter