L
loukas_t
Hi all,
Three questions:
1. What the constraint A<B,C means and how can I entering in the MSP?
2. I have 3 kinds of human resources. Lets say for example, kind A are
engineers. I have 8 of them and everyone is costing 1500 Euros/month.
Task A needs 4 engineers. How can I assign them to the task and add the
appropriate cost?
3. I have 3 machines as a resource. Each machine has a usage cost of
3000 euros per task and function cost 2400 euros per month. How can I
assign them in the appropriate tasks? And how can I distribute their
cost?
Thank you in advance
Three questions:
1. What the constraint A<B,C means and how can I entering in the MSP?
2. I have 3 kinds of human resources. Lets say for example, kind A are
engineers. I have 8 of them and everyone is costing 1500 Euros/month.
Task A needs 4 engineers. How can I assign them to the task and add the
appropriate cost?
3. I have 3 machines as a resource. Each machine has a usage cost of
3000 euros per task and function cost 2400 euros per month. How can I
assign them in the appropriate tasks? And how can I distribute their
cost?
Thank you in advance