J
Joe
Hi,
I just upgraded my project from 2003 to 2007 version and now I have trouble
importing data from Excel to MSP 2007. What I'm trying to do is to import %
Work Complete from Excel to Project 2007 (Which I usually do on MSP 2003
without problem) using the Project Import Wizard, the % Work Complete did not
import but surpising that my Actual Work was calclulated according to the %
Work Complete I'm importing after the import process.
I'm not sure what I did wrong, I been doing this for years and years in MSP
2003 and don't have problem. Please help.
Joe V
I just upgraded my project from 2003 to 2007 version and now I have trouble
importing data from Excel to MSP 2007. What I'm trying to do is to import %
Work Complete from Excel to Project 2007 (Which I usually do on MSP 2003
without problem) using the Project Import Wizard, the % Work Complete did not
import but surpising that my Actual Work was calclulated according to the %
Work Complete I'm importing after the import process.
I'm not sure what I did wrong, I been doing this for years and years in MSP
2003 and don't have problem. Please help.
Joe V