A
Andy
I am trying to set up Microsoft Project Server 2000 and I
use MSP 2000. I am trying to set it up so that it
notifies resources via email when they have new tasks
assigned. I have one person who is acting as a "guinea
pig" while I am trying to set up the system for email
notification. I thought that I had it set up correctly,
and when I assigned new tasks to this resource it gave me
a dialog box with the option to change the text and it
appeared to send the email when I was through. The
particular resource has not recieved any emails, and I
have repeated this process several times. The person also
doesn't receive any of the status updates that I have
tried to send. I have not used Project Server before and
I have limited access to our technical support team.
Any suggestions would be greatly appreciated.
Thanks,
Andy
use MSP 2000. I am trying to set it up so that it
notifies resources via email when they have new tasks
assigned. I have one person who is acting as a "guinea
pig" while I am trying to set up the system for email
notification. I thought that I had it set up correctly,
and when I assigned new tasks to this resource it gave me
a dialog box with the option to change the text and it
appeared to send the email when I was through. The
particular resource has not recieved any emails, and I
have repeated this process several times. The person also
doesn't receive any of the status updates that I have
tried to send. I have not used Project Server before and
I have limited access to our technical support team.
Any suggestions would be greatly appreciated.
Thanks,
Andy