Microsoft Project should account for resources in different time z

K

Katoblepa

I work in a software develpment company as a Localization Project Manager.
We have teams spread around the globe on several time zones working on the
same project.
It would be very usefull if timezone could be taken into account.
For example, if a build is done in Europe, QA could in fact start the same
date if it's handled in the US West Coast.
I currently have to handle these very frequen situation manually adding a
negative lag to the QA task. This is a problem, though, if I have to change
QA team to another one in a different time zone.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/com...13fb6a4&dg=microsoft.public.project.developer
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top