D
Deepak_Malhotra
Dear All
I have one query regarding the Microsoft Project.
I have created a project plan, i have set the base line as well. now
want to show the delay of each task.. how can i do that.
Say one of my task started on March 19, 2010 and was supposed to finis
on March 22, 2010.
However, the task started on time but finished on March 30, 2010. so
want to show the delay of 8 days in the project plan...
How can i do that... please help..
I have one query regarding the Microsoft Project.
I have created a project plan, i have set the base line as well. now
want to show the delay of each task.. how can i do that.
Say one of my task started on March 19, 2010 and was supposed to finis
on March 22, 2010.
However, the task started on time but finished on March 30, 2010. so
want to show the delay of 8 days in the project plan...
How can i do that... please help..