Value of Work (Scheduled Performance Indicator (SPI)). Basically the
difference between Cumulative Work (BCWS) and the Earned Value of Worked
Accomplished (BCWP). It's a number which informs us if a contract is on the
projected schedule.
I already have the program calculating BCWP. I need the BCWS (the projected
cumulative hours to date) to complete the formula.
Already tried. They don't calculate to the values I need. This corporation
doese EVMS reporting a little different. Most of the values I had to
manually formulate.
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.