Can anyone please tell me how to fix or prevent task assignments from blowing
up (actual work spreading around, remaining work blowing up, etc) in migrated
projects? We have:
* Followed all pre-migration preparation steps
* Installed all updates and CUs on 2007 and client workstations (except for
the 12/09 CU).
* Removed and replaced all 2003 calendars with exact same 2007 calendars.
We had a small handful of project tasks that didn't migrate right and fixed
them manually. That's not a problem as many of the assignments were corrupt
in 2003. The real problem is that entering and updating time is doing what
it has been all along and it is supposed to be fixed. This does not happen
with new installs.
Please help. This was supposed to have been fixed each of the last four
updates (sorry, just ranting a bit).
up (actual work spreading around, remaining work blowing up, etc) in migrated
projects? We have:
* Followed all pre-migration preparation steps
* Installed all updates and CUs on 2007 and client workstations (except for
the 12/09 CU).
* Removed and replaced all 2003 calendars with exact same 2007 calendars.
We had a small handful of project tasks that didn't migrate right and fixed
them manually. That's not a problem as many of the assignments were corrupt
in 2003. The real problem is that entering and updating time is doing what
it has been all along and it is supposed to be fixed. This does not happen
with new installs.
Please help. This was supposed to have been fixed each of the last four
updates (sorry, just ranting a bit).