Migrating from MS Project 2003 server to MS Project 2007 server

I

Ian Bertram

This one is killing me. After running the MS Project Server 2003 to MS
Project Server 2007 migration, all resources within projects are set to
their default "committed" or "Proposed" status. We use the resource
"committed" or "Proposed" feature of MS Project 2003 extensively, but after
the projects are migrated to MS Project 2007 ,the resource setting (in every)
project are reset to the default Proposed/Committed setting attached to the
resource in the Enterprise Resource pool. You indivdual project resource
setting are lost.. I cannot belive that other MS Project accounts have not
encountered this problem. But even with MS partner help I have been upable
to find a solution. Please help

url:http://www.ureader.com/gp/1119-1.aspx
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top