J
John_JXL
I am evaluating migrating from a current solution based on 7 separate plans
on Standard 03 (i.e. without PS) to a PS07 based solution.
Can I migrate the separate 03 plans directly onto the PS07 server - can I
still operate the 7 plans separately on the server based solution (but
potentially with pooled resourcing, etc.) such that the 7 project managers
can independently manage and update their plans separately?
Secondly would a logical first step for the migration be to upgrade everyone
to MS07 professional (but operating in standalone mode) before I set up the
project server? This seems to be a quick first steps which gets everyone
using MS07 first before we migrate onto the project server solution?
Thanks,
John.
on Standard 03 (i.e. without PS) to a PS07 based solution.
Can I migrate the separate 03 plans directly onto the PS07 server - can I
still operate the 7 plans separately on the server based solution (but
potentially with pooled resourcing, etc.) such that the 7 project managers
can independently manage and update their plans separately?
Secondly would a logical first step for the migration be to upgrade everyone
to MS07 professional (but operating in standalone mode) before I set up the
project server? This seems to be a quick first steps which gets everyone
using MS07 first before we migrate onto the project server solution?
Thanks,
John.