migration issues : percentage complete coming wrong

R

rohit barde

Hi,
I have migrated around 100 plans from msp 2003 to 2007. what i have noticed
is in many projects % complete is coming wrong after migration though
duration, start date and finish date seems to be ok. i have installed sp1 for
project 2007 but not infrasttucture update. can any one please help me in
finding solution for this?
 
R

rohit barde

To correct myself:
duration is coming wrong and it is affecting percentage complete. though
start and end dates are ok.
 
M

Mike Mahoney

To correct myself:
duration is coming wrong and it is affecting percentage complete. though
start and end dates are ok.





- Show quoted text -

rohit

If start and end dates are the same and durations are different then
there must be different calendars at work.

regards

Mike
 
R

rohit barde

Hi Mike,
Thnaks for your response.
I have checked calendars are same in both 2003 and 2007.
and it is not happening with all tasks. if there are 100 tasks it is
happening with
around 3-4. and it is making duration as 0 for those tasks.
 
M

Mike Mahoney

Hi Mike,
Thnaks for your response.
I have checked calendars  are same in both 2003 and 2007.
and it is not happening with all tasks. if there are 100 tasks it is
happening with
around 3-4. and it is making duration as 0 for those tasks.





- Show quoted text -

Hi Rohit

Some areas of investigation:
Do any of these tasks have task calendars?
Is it only a problem for progressed tasks or any task?
Do problem tasks have multiple resource assignments
On problem tasks, do assignment profiles change?

See "Resolutions for issues that occur during migration from Project
2003 to Project 2007" in KB953750 (IU)

regards

Mike
 