Chris
Hi
We have just gone live on project Server using Timesheets and managed
periods and i am having a problem!
The milestones in plans are not resourced, however when i try to flag them
as complete in the plan i am told my action may result in the plan being out
of synch with actuals - i save and the milestone is zero % complete again!
Any ideas?
Regards
Chris.
We have just gone live on project Server using Timesheets and managed
periods and i am having a problem!
The milestones in plans are not resourced, however when i try to flag them
as complete in the plan i am told my action may result in the plan being out
of synch with actuals - i save and the milestone is zero % complete again!
Any ideas?
Regards
Chris.