Milestone Completion

C

Chris

Hi

We have just gone live on project Server using Timesheets and managed
periods and i am having a problem!

The milestones in plans are not resourced, however when i try to flag them
as complete in the plan i am told my action may result in the plan being out
of synch with actuals - i save and the milestone is zero % complete again!

Any ideas?

Regards

Chris.
 
D

Dale Howard [MVP]

Chris --

You need to update Project Server and Microsoft Project Professional to
SP2a. This issue was present in Project Server prior to SP1. Hope this
helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top