Milestone Completion

  • Thread starter projectserverdragon
  • Start date
P

projectserverdragon

I have 4 tasks in a plan where task 4 is a milestone w/ a zero hour work
value and zero day duration.
Task 4 is a successor to tasks 1-3.
When I update tasks 1-3 to 100% complete task 4 does not update to 100%
complete.

Any idea why????
 
J

JulieS

Hello projectserverdragon,

You'll need to mark the milestone as 100% complete manually. Just
because a task is a successor to another task, it does not inherit %
complete from it's predecessor. Only summary tasks will go to 100%
complete upon the completion of all subtasks.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"projectserverdragon" <[email protected]>
wrote in message
news:[email protected]...
 
C

Connie

Is it possible to have several independent tasks be predecessors to a
milestone, and have the milestone automatically reflect the % complete.

For example
milestone #1 (predecessors 1,5,9) 35% complete (Automatically updated if the
tasks change)
task 1 40% complete
task 5 20% complete
task 9 10% complete
 
J

JulieS

Hello Connie,

No, sorry. The only tasks whose percentage complete are changed by
other tasks percentage complete are summary tasks. Percentage
complete of predecessors does not impact percentage complete of
successor tasks.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top