I have 4 tasks in a plan where task 4 is a milestone w/ a zero hour work
value and zero day duration.
Task 4 is a successor to tasks 1-3.
When I update tasks 1-3 to 100% complete task 4 does not update to 100%
complete.
Any idea why????