D
Darrell
I have not been able to find an answer to this so I will ask again.
I have seen several project schedules from several different project
managers where a tasks duration suddenly jumps out into the future without
anyone knowing why. I just worked with a PM who removed a generic resource
that was mistakenly assigned to a milestone and when the generic resource was
removed the duration changed to 1000 something days and the finish date went
to 2049 even thought the task had zero duration and zero work and zero
progress prior to removing the resource. What is causing this behavior?
Darrell
I have seen several project schedules from several different project
managers where a tasks duration suddenly jumps out into the future without
anyone knowing why. I just worked with a PM who removed a generic resource
that was mistakenly assigned to a milestone and when the generic resource was
removed the duration changed to 1000 something days and the finish date went
to 2049 even thought the task had zero duration and zero work and zero
progress prior to removing the resource. What is causing this behavior?
Darrell