I am making a master project sheet that summarizes many sub projects. I need
to link the milestones to the master project sheet from the sub project
sheet. When I link these milestones, many additional, non desired lines are
copied/linked onto the master project. In addition, these milestones are
portrayed at a date that does not corespond with the original date of the sub
project. The sub project is dated long in the past and when linked, they are
moved in the master project to the current date.
Help!!!