Hi assaf1978,
Welcome to this Microsoft Project newsgroup
The summary task Duration shows the number of working days between the start
of the first task to the end of the last task. Milestones by definition
consume no time or resources (one could argue that they're not even Tasks).
If you create a schedule with no tasks and no work, Project doesn't know how
to handle it. What you have told it is that 3 milestones have 100% of the
Duration allotted to them as being complete. As milestones consume no time,
100 %Complete is rather an anomaly in the timeline. It is thus difficult
for Project to summarize %Complete overall, if nothing has been done. The
best it can do is to show 100%Complete when all the milestones have been
100%Complete, but progress towards this is not computed as no time has been
consumed. I'm sure someone else can give you a better explanation, but
that's how I see it!
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for my free Project Tutorials