Milestone Status Notifications

A

Alex

Hi

I have seen a question posted (see link below) that suggests a solutions to Milestone Status Notification. Below the link also the important extract taken from the response given by Gary Chefetz. I am enquiring as to whether anyone can elaborate on this a little, for example does it just need tweaking in PWA Admin and if so how? or does it require custom fields being set up in Project? Or does it require some actual tweaking in the code?

http://www.google.com/[email protected]&rnum=
Is there a capability for automatic Milestone status notification
That is, can you set up Project to give you an automatic notificatio
that a key milestone has been met or missed
Yes, it takes a little finessing with the notification and reminders engine

Thank
 
D

Dale Howard [MVP]

Support --

If you can help this person, then why don't you post the answer in the
newsgroup so that everyone can benefit? This newsgroup is a forum where we
all help one another publicly. I would suggest you start posting some real
answers instead of merely advertising your services.




support said:
I am from the MS Project / Project Server 2002/2003 support department at
http://www.enterpriseprojectconsulting.com and we would be happy to assist
you in resolving your issue.
 
E

Earl Lewis

Dale,

I know you're heart is in the right place but we shouldn't even acknowledge
this kind of solicitation with the honor of a response. Clearly this person
doesn't understand what this NG is about and any reply can only serve to
encourage them.

Maybe the NG moderators will be good enough to remove them as they do with
other spam.;>)

Earl
 
G

Gary L. Chefetz \(MVP\)

Alex:

Experiment with assigning a resource to a milestone and/or using a milestone
completion task ahead of the milestone. Then set reminders accordingly.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts

-
Alex said:
Hi,

I have seen a question posted (see link below) that suggests a solutions
to Milestone Status Notification. Below the link also the important extract
taken from the response given by Gary Chefetz. I am enquiring as to whether
anyone can elaborate on this a little, for example does it just need
tweaking in PWA Admin and if so how? or does it require custom fields being
set up in Project? Or does it require some actual tweaking in the code?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.