I am creating a Gantt chart for events that will occur in the future. When I
add tasks or milestones, the start date is always the date I am creating the
chart. For example, I am creating a chart on 8/15. The beginning of the chart
is 9/1. When I create milestones or taskbars, they seem to disapear, because
they start on 8/15, before the start date of the chart. I can find them with
the Drawing explorer, view the custom properties and change the start date
there, but that's pretty roundabout. Is that normal behavior for Visio 2003,
and is there any way to change this behavior. (or an easier way to find my
milestones)
add tasks or milestones, the start date is always the date I am creating the
chart. For example, I am creating a chart on 8/15. The beginning of the chart
is 9/1. When I create milestones or taskbars, they seem to disapear, because
they start on 8/15, before the start date of the chart. I can find them with
the Drawing explorer, view the custom properties and change the start date
there, but that's pretty roundabout. Is that normal behavior for Visio 2003,
and is there any way to change this behavior. (or an easier way to find my
milestones)