Hi all,

Is there a way for me to extract the milestones from the project plan and
populated it into a list in the project workspace on WSS? I've try to figure
out any possibility, but I'm bumped! Any help is very much appreciated.

Regards,
Azwan
 
G

Gary L. Chefetz [MVP]

Azwan:

You can set a filter on a project display in both Project and PWA to filter
on milestone=yes. From such a view, you can copy data and paste it into a
list using the explorer view.
 