Benjiluck
already established the differences between task using Flags, which allows me
The calendar view has far fewer features than the Gantt Chart view, and the
ability to do what you want does not exist - sorry
Some say you can do anything with vba, so try posting on the developer
newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
products and other useful Project information can be seen at this web
address: http://project.mvps.org/faqs.htm
So sorry, I missed the fact that it was the calendar viewto colour bar and milestones in the Gantt chart but still can't
achieve this in Calendar view. Any colour change I make to milestones
in calendar results in all changing.
Any ideas how i seperate out my milestones in the calendar view based
on the fact that i have differences between my milestones due to
resource allocations?
Any help would be really appreciated.
Ben
The calendar view has far fewer features than the Gantt Chart view, and the
ability to do what you want does not exist - sorry
Some say you can do anything with vba, so try posting on the developer
newsgroup. Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
products and other useful Project information can be seen at this web
address: http://project.mvps.org/faqs.htm