C
Chris_J_S
I opened my file and a whole bunch of my milestones where converted to tasks.
It appears (though I can't be sure) that it was only done for milestones
that had durations greater than 0. This has happened more than once. Has
anybody else seen this phenomenom and have a suggestion for what we can do to
prevent it from occuring in the future? I've been MS-Project since '94 and I
never saw this before. As background, this particular file is stored on
Project Server (V2007) and we do have SP1.
It appears (though I can't be sure) that it was only done for milestones
that had durations greater than 0. This has happened more than once. Has
anybody else seen this phenomenom and have a suggestion for what we can do to
prevent it from occuring in the future? I've been MS-Project since '94 and I
never saw this before. As background, this particular file is stored on
Project Server (V2007) and we do have SP1.