A
Andy S
I am working with Project Pro 2007.
When I create a schedule from Project Start Date (found under Project -
makes sense to me, as a milestone has zero duration.
However, when I schedule from Project Finish Date, a milestone in my
schedule will list the earliest start and latest finish date of the
entire schedule (assuming no dependencies to the milestone). The
duration still is listed as zero.
Additionally, if the milestone does have dependencies tied to it, the
start and finish dates will still be at least one day apart. The
duration is still listed as zero, once again.
I do not see this same occurrence in Project Pro 2003.
When I create a schedule from Project Start Date (found under Project -
lists the same date under the start and finish date columns. ThisProject Information -> Schedule From), a milestone in my schedule
makes sense to me, as a milestone has zero duration.
However, when I schedule from Project Finish Date, a milestone in my
schedule will list the earliest start and latest finish date of the
entire schedule (assuming no dependencies to the milestone). The
duration still is listed as zero.
Additionally, if the milestone does have dependencies tied to it, the
start and finish dates will still be at least one day apart. The
duration is still listed as zero, once again.
I do not see this same occurrence in Project Pro 2003.