Hi

Can Anyone advise me how to make Milestones appear on the rollup
bars. ?

They also appear in the lines below the rollup bar when you expanded.


thanks in Advance

Martin
 
J

Jack Dahlgren

Double click the milestone and the task information window will open.
Select the "general" tab and check the option "Rollup Gantt bar to summary"

That should generally do it. You may need to modify the bar style for rolled
up milestone tasks, but the default views have one already.

-Jack Dahlgren
 