P
PSW
Hi folks
The problem.
Management meetings (where finance decisions are made outside of the
project) are only held on Mondays - so a milestone exists, with no resources,
on the first Monday after a given task, the next task cannot begin until the
day after that meeting.
I thought I could get around this by creating a meeting calendar with just
Mondays as working days and assigning it to the milestone.
However, a zero time milestone seems to ignore the calendar constraint
completely and if I make it a task of 1 minute duration (marked as a
milestone) it throws out the stage by adding .75 of a day to elapsed
time......?
What am I missing?
The problem.
Management meetings (where finance decisions are made outside of the
project) are only held on Mondays - so a milestone exists, with no resources,
on the first Monday after a given task, the next task cannot begin until the
day after that meeting.
I thought I could get around this by creating a meeting calendar with just
Mondays as working days and assigning it to the milestone.
However, a zero time milestone seems to ignore the calendar constraint
completely and if I make it a task of 1 minute duration (marked as a
milestone) it throws out the stage by adding .75 of a day to elapsed
time......?
What am I missing?