Milestones

F

Fayez

Hi
Using MS Project 2000, is there a way to show milestone (Must be on) at the
end of the working day instead of the beginning of the day?

I have tried to go Bar and select milestone to be "finish to finish" instead
of being "start to start by default" but there was no effect.

Thanks in advance
Fayez
 
M

Mike Glen

Hi Fayez,

Welcome to this Microsoft Project newsgroup :)

Tools/Options.../View tab and select a Date Format that includes the time of
day. Then, when setting up the milestone constraint, type in the date and
time you want.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP
 
J

Jan De Messemaeker

Hello Fayez,

It all depends on how exactly you fill in "Must be On" (which as such is not
one of the constraints available)
If you choose "Must Start On" the date/time is start of day
If you choose "Must Finish On" Project uses end of day

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads


Top