F
Fayez
Hi
Using MS Project 2000, is there a way to show milestone (Must be on) at the
end of the working day instead of the beginning of the day?
I have tried to go Bar and select milestone to be "finish to finish" instead
of being "start to start by default" but there was no effect.
Thanks in advance
Fayez
Using MS Project 2000, is there a way to show milestone (Must be on) at the
end of the working day instead of the beginning of the day?
I have tried to go Bar and select milestone to be "finish to finish" instead
of being "start to start by default" but there was no effect.
Thanks in advance
Fayez