I want to display an extra marker on my milestone line on the gantt chart. I
have one marker for "baseline start" and one for "start." I also need a
marker that indicates that the baseline start recieved an extension. I tried
adding a new column "baseline2 start" and giving it a marker, but then the
marker for "baseline start" disappeared (though the date that normally
appears beside it didn't) and I can't seem to get it to reappear even by
hiding the "baseline2 start" column.

I'm pretty new to project and any help with this would be great. Thanks.
 
J

Jan De Messemaeker

Hi,

Columns have no bearing to what appears on teh Gantt Chart.
I advice reading of FAQ 31: Customizing Task Bars; URL of the FAQs in my
signature.

HTH
 

Ask a Question