F
Franco Lombardo
I have some questions about Project 2007.
1) I have a plan with a deep outline structure. Is there a way to ask Projec
to expand/collapse the outline tree till the n-th level?
2) Is it possible to customize the Gantt view in order to show different
outline levels with different colors? I mean, I'd like to see all the
summary task at the first level in blue, all the ones at the second in red,
and so on.
3) Is there a way to center the Gantt View on the period in wich a
particular task wil be executed?
Thanks a lot.
Bye.
Franco
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
http://www.francolombardo.net
Scala, Java, As400.....
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
1) I have a plan with a deep outline structure. Is there a way to ask Projec
to expand/collapse the outline tree till the n-th level?
2) Is it possible to customize the Gantt view in order to show different
outline levels with different colors? I mean, I'd like to see all the
summary task at the first level in blue, all the ones at the second in red,
and so on.
3) Is there a way to center the Gantt View on the period in wich a
particular task wil be executed?
Thanks a lot.
Bye.
Franco
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
http://www.francolombardo.net
Scala, Java, As400.....
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~