M
miniME
In Microsoft Project, I have the following 2 tasks:
Task A | Duration = 1d | Start & Finish = Tue 12/02/08 | Resource = Dummy[50%]
Task B | Duration = 0.5d | Start & Finish = Tue 12/02/08 | Resource =
Dummy[100%]
Assuming Dummy works 8 hours a day, on Tue 12/02/08, he is allocated to Task
A for 4 hours and Task B for 4 hours and this is reflected correctly on the
Task Usage page.
However, if you look at the Resource Graph page, Dummy is actually 150%
allocated on Tue 12/02/08 and is showing that he is being overallocated,
which is not true.
Is there options / settings I could change to make the Resource Graph page
showing the true allocation? Or am I missing something here?
Thanks!
Task A | Duration = 1d | Start & Finish = Tue 12/02/08 | Resource = Dummy[50%]
Task B | Duration = 0.5d | Start & Finish = Tue 12/02/08 | Resource =
Dummy[100%]
Assuming Dummy works 8 hours a day, on Tue 12/02/08, he is allocated to Task
A for 4 hours and Task B for 4 hours and this is reflected correctly on the
Task Usage page.
However, if you look at the Resource Graph page, Dummy is actually 150%
allocated on Tue 12/02/08 and is showing that he is being overallocated,
which is not true.
Is there options / settings I could change to make the Resource Graph page
showing the true allocation? Or am I missing something here?
Thanks!