Mismatch in Email Notifications

M

MartinR

Has anyone encountered an issue with the start and end dates of tasks in
email notifications not matching the start and end dates in the project?

Martin
 
G

Gary L. Chefetz [MVP]

Martin:

This can be explained by project data not being fully published to the
server. The moment you start making changes to a project plan, the two
become out of synch until the new information is published. Partial failure
in publishing is a possible explanation as well. Also, don't forget that the
email notices are at the assignment level, and assignment start and end
dates are specific to a resource and task combination and may rightfully
never match the start and end dates displayed for the tasks in the plan when
more than one resource is assigned to a task.
 
M

MartinR

Thanks Gary

Gary L. Chefetz said:
Martin:

This can be explained by project data not being fully published to the
server. The moment you start making changes to a project plan, the two
become out of synch until the new information is published. Partial failure
in publishing is a possible explanation as well. Also, don't forget that the
email notices are at the assignment level, and assignment start and end
dates are specific to a resource and task combination and may rightfully
never match the start and end dates displayed for the tasks in the plan when
more than one resource is assigned to a task.
 