Missed Deadline Indicator not showing

C

CycleFitness

I am setting deadline dates which have expired and the missed deadline
indicator is not showing up in the indicator column. Can anybody help me to
understand why?

Thanks!
 
J

JulieS

Hello CycleFitness,

Has the finish date of the task passed the deadline date? Try
inserting the deadline field (Insert > Column) to double check the
deadline date and compare it to the finish date of the task.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
J

JulieS

Thanks for that confirmation. What version of Project are you using
including service pack? Does this happen on all files or just one in
particular?

Julie
 
S

Steve House

Have you used the "Reschedule Uncompleted Work" tool in the Tracking menu to
move those task up to the date when you think they'll be able to start or
are they still sitting back there on the dates where they were originally
scheduled? Project don't really know much about the current date. If we
have a 1-day task originally scheduled for last Monday with a deadline of
last Wednesday sitting in the schedule, if it still shows on Monday the
missed deadline indicator doesn't light up even if the task is not marked as
complete. Only when the task gets moved - pushed by a predecessor or by
rescheduling so it falls in the schedule on a date later than the deadline
date does the indicator turn on. The current date doesn't enter into it at
all.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top