Missing contour option

P

Peter Janssens

Hi,

I am using the Dutch version of MSP 2003 professional. Normally, it is
possible to assign a workcontour (flat, front-loaded, ...) to a resource.

When I double-click on the resource in a Task usage view, the dropdown box
to select the contour is not visible. It is hoverever possible to enter work
in the timephased window. The indicator shows then the icon of a edited
workcontour.

Any suggestions?

Thanks
 
R

Rod Gill

Is the contour available in the Resource Usage view by double-clicking a
task name?
 
P

Peter Janssens

Rod,

No, the contour is not available in the resource usage or task usage view.
All I see (when I diuble-click a task in teh resource usage view), is the
label. In Dutch, it is called "werklastbeschrijving:". There is no
possibility to select one of the predefined options: there is simply no
drop-down.

May be, it has something to do with the Dutch version? Or is it some option
with the professional version. I use it as a stand-alone version (therefore,
I 'd better shoudl use the Standaard version, but this is the one I got from
work). I don't use Microsoft Server 2003.

Thanks for your time.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top