Peter Janssens
Hi,
I am using the Dutch version of MSP 2003 professional. Normally, it is
possible to assign a workcontour (flat, front-loaded, ...) to a resource.
When I double-click on the resource in a Task usage view, the dropdown box
to select the contour is not visible. It is hoverever possible to enter work
in the timephased window. The indicator shows then the icon of a edited
workcontour.
Any suggestions?
Thanks
I am using the Dutch version of MSP 2003 professional. Normally, it is
possible to assign a workcontour (flat, front-loaded, ...) to a resource.
When I double-click on the resource in a Task usage view, the dropdown box
to select the contour is not visible. It is hoverever possible to enter work
in the timephased window. The indicator shows then the icon of a edited
workcontour.
Any suggestions?
Thanks