D
Doug
We update the OLAP cube every day at 12:00 noon (using the "Use the
earliest project start date and the latest project finish date" and
"Use the following date range for retrieving resource availability
information: Next 4 weeks, past 0 weeks"). This process has been
running, with these settings, for the past couple of years without
issue. As of late last week the data in the OLAP was good. However,
at some point between last week and today, most of the data within the
OLAP is now missing. Running the update again using the "Update Now"
button does not change the results. The data is still present within
the project schedules in project server, but for some reason most (but
not all) data in the cube is gone. Any ideas as to what would cause
this, and more importantly, what I can do to repopulate the cube?
Thanks.
earliest project start date and the latest project finish date" and
"Use the following date range for retrieving resource availability
information: Next 4 weeks, past 0 weeks"). This process has been
running, with these settings, for the past couple of years without
issue. As of late last week the data in the OLAP was good. However,
at some point between last week and today, most of the data within the
OLAP is now missing. Running the update again using the "Update Now"
button does not change the results. The data is still present within
the project schedules in project server, but for some reason most (but
not all) data in the cube is gone. Any ideas as to what would cause
this, and more importantly, what I can do to repopulate the cube?
Thanks.