Hi,
In Portfolio Analyzer Views, Actual Work Protected data is missing for one
Project. That too It's showing data till 2007 but not for 2008 only
in that particular Project. For Remaining all Projects its showing up to
date
correct data.

But its showing Data of Actual work in MPP & all information have published
to project Server.

what will be the issue? Can you help me with this?

Thanks & Regards,
Jaya
 
C

Chak

Hello Jaya,

Have you verified the AW & AWP values in MS project plan. If you
didn't see AWP values, you may be use sync feature to write the actual
work values into actual work protected columns.

Once you make sure the Actual Work and Actual Work Protected values
matches and appears on project plan, publish the project plan. Also
make sure OLAP cube build before you verify the values in Portfolio
Analyzer.

Additional reference on AW & AWP:

http://www.epmcentral.com/pjadmin/protactuals.php


Thanks
Chak
http://www.epmcentral.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top