Missing Field when exporting to Excel.

F

Frank J.

From Resource Center select resource(s)

Then click “View Availabilityâ€

From settings select date range and units

In addition to graph, you receive data related to what projects and related
project hours each person you select will be working on for the date range
you selected… so far perfect.

Now export to excel… task and task hours are there…. But resource name is
missing. Is this a bug??? Or the way it’s supposed to work. How can I get
this information into excel
 
G

Gérard Ducouret

Hi Frank,

It's a reported bug. We expect it will be fixed in SP1...

Gérard Ducouret
 