Missing Months in PWA Portfolio Analyzer

  • Thread starter Ncrease MSProject consultant
  • Start date
N

Ncrease MSProject consultant

I'm using two environments Project Server 2002 & 2003. In each, when I
display 2006 Year in Analyzer the Q4 only contains October & November? I
definitely have work past Nov. and into calendar year 2007. I looked at the
calendar tab and the Enterprise options but couldn't find a fix. Help!
Thanks!
 
G

Guidho

For Project Server 2003:
Log in as administrator. Go to Admin -> Manage Enterprise Features where
you can review and specify cube building settings.

Review the Cube Building timeframe settings. This probably shows
something like [Past 4 weeks - Next 4 weeks]

Change this to a bigger timeframe and Build the OLAP cube again.

Hope this helps,
Guidho
 