Missing My Tasks time ---Mystery

A

anovak

We are on SP2 and June Cumulative. Are there still some bugs out
there that you know of that cause (unaccepted) My Tasks entries
disappear suddenly with no explanation?

Thanks,
Andy Novak
University of North Texas
 
R

reza

Anovak...

In my opinion, there are 2 possibility...
Maybe all task not published yet or all task is administrator owner.
1. open project in ms pro then insert publish coloum. Set yes to all
task---save and publish again.
2. Or that task is adminitrator owner. go to task usage then insert
Assignment Owner Coloum, see the owner of all task.

If both of my answer didn't help, please forgive me maybe others can share
their knowledge about this.

thanks

reza
 
J

JenStover

We are experiencing this very same problem....only we're seeing it actually
happen with accepted and published time as well. In cube one day, gone the
next.

We have a ticket open with Microsoft but have no resolution at this point.

We just upgraded at the end of July. We are patched up through CU2. When
did you notice it start to happen?
 
A

andy.novak

We are experiencing this very same problem....only we're seeing it actually
happen with accepted and published time as well.  In cube one day, gonethe
next.  

We have a ticket open with Microsoft but have no resolution at this point..

We just upgraded at the end of July.  We are patched up through CU2.  When
did you notice it start to happen?

Its been off and on even after SP2 and June Cumulative
 
J

JenStover

Andy - are you seeing it in projects that were 'Admin' plans in MS Project
server 2003?
 