My post from a few days ago seems to be missing?! I've searched all through
the headers and can't find it, so excuse the repitition, if it exists.
We're trying to schedule production jobs here at work. We might have a
stage that will run for a few days, say "machining". In a monthly view you
click and drag to make the item say 3 days long. E.g. Wed,Thurs,Fri = one
item. Works fine, but say we reschedule and want to move it back one day,
we would like it to flow around the weekend (Sat & Sun). At the moment, we
would have to break it up as two items Thurs,Fri + Mon. Eben if we created
and original item that was Thurs,Fri,Mon, we'd still have to break it up.
Just slows down the whole process, especially with may jobs and many stages.
Is there any way (literally!) around this?
Again, sorry for the repost - love to know where the original went.
Johnathan.
My post from a few days ago seems to be missing?! I've searched all through
the headers and can't find it, so excuse the repitition, if it exists.
We're trying to schedule production jobs here at work. We might have a
stage that will run for a few days, say "machining". In a monthly view you
click and drag to make the item say 3 days long. E.g. Wed,Thurs,Fri = one
item. Works fine, but say we reschedule and want to move it back one day,
we would like it to flow around the weekend (Sat & Sun). At the moment, we
would have to break it up as two items Thurs,Fri + Mon. Eben if we created
and original item that was Thurs,Fri,Mon, we'd still have to break it up.
Just slows down the whole process, especially with may jobs and many stages.
Is there any way (literally!) around this?
Again, sorry for the repost - love to know where the original went.
Johnathan.