J
jay
Desktop: MS Project Professional 2002 SP-1
Server: MS Project Server 2003 SP-1
Season's Greetings,
The project manager of a checked-out enterprise project recently encountered
the Microsoft Project error:[Microsoft][ODBC SQL Server Driver][SQL
Server]Disallowed implicit conversion from data type datetime to date type
decimal, table 'ProjectServer.dbo.MSP_RESOURCES_PROJ_WRITEVIEW',column
'RES-OVT-COST'. Use the CONVERT function to run this query. After selecting
'OK', the project was saved and then closed. When the project was
checked-out again, ALL the resources were missing...!!
The project has in excess of 3200 line items, has been executing for 6
months, is 3 weeks from completion and has approx 40 resources. In terms of
troubleshooting, the project manager's ODBC driver is at the appropriate
version level. The SQL Server DBA found nothing in the logs that suggested
any db problems and a CHECKDB yielded 0 problems in the db. We are unable to
duplicate the problem (tested on 2 desktop configurations). So... the
project manager has re-Built Team from Enterprise and established assignments
for the outstanding work...
Stating the obvious - we are concerned about the stability/integrity of the
project. On the upside, hours have been accepted and (apparently
successfully) updated against the project. No other problems have been
reported associated with any of the other enterprise projects...should we be
concerned about the stability of our server environment?...advice is welcomed!
Thank you
Jay
Server: MS Project Server 2003 SP-1
Season's Greetings,
The project manager of a checked-out enterprise project recently encountered
the Microsoft Project error:[Microsoft][ODBC SQL Server Driver][SQL
Server]Disallowed implicit conversion from data type datetime to date type
decimal, table 'ProjectServer.dbo.MSP_RESOURCES_PROJ_WRITEVIEW',column
'RES-OVT-COST'. Use the CONVERT function to run this query. After selecting
'OK', the project was saved and then closed. When the project was
checked-out again, ALL the resources were missing...!!
The project has in excess of 3200 line items, has been executing for 6
months, is 3 weeks from completion and has approx 40 resources. In terms of
troubleshooting, the project manager's ODBC driver is at the appropriate
version level. The SQL Server DBA found nothing in the logs that suggested
any db problems and a CHECKDB yielded 0 problems in the db. We are unable to
duplicate the problem (tested on 2 desktop configurations). So... the
project manager has re-Built Team from Enterprise and established assignments
for the outstanding work...
Stating the obvious - we are concerned about the stability/integrity of the
project. On the upside, hours have been accepted and (apparently
successfully) updated against the project. No other problems have been
reported associated with any of the other enterprise projects...should we be
concerned about the stability of our server environment?...advice is welcomed!
Thank you
Jay