Hi there,

I'M using the view where you can see the ressources ==> tasks. So I can see
the planned costs for a ressource in the timephased data for a specific task.
That's no problem, but there is no sum for the whole ressource. I need to
summarize all the tasks to get the planned costs. Why is that? How can I see
these sums?

2003 prof SP2

Best regards

Michael
 
J

Jan De Messemaeker

Hi Hans/Michael,

It would definitely help if you would anwswer John's question: which cost
are you looking at? What is the label of the lines in the Usage View?
 
H

Hans Wurst

Hi Jan,

at this thread I'm talking about planned costs in the ressource usage view.
The timephased data of planned costs is not summarized.

I do also not load data from other projects. I don't know the English
expression for the checkbox you select while connecting to Projet Server, but
do you know what I mean?

Best regards

Michael
 
J

Jan De Messemaeker

Hi,

I don't think Server could play a role here but in normal Project Pro Costs
ARE totalized (timescaled)
HTH
 
H

Hans Wurst

exactly that's my problem ;-)

Jan De Messemaeker said:
Hi,

I don't think Server could play a role here but in normal Project Pro Costs
ARE totalized (timescaled)
HTH
 
J

Jan De Messemaeker

Hi,

Could you send the file to jandemesATprom-adeDOTbe?
I'll try to find out.
There is no common reason to this.