Missing Task updates

B

Bhanu Prasad

Hi all,

I have just started working and evaluting Project Server 2007.
I am able to save and publish a project onto the project server.

When the team members logon and update their tasks via PWA, the updates are
not reflected into the Office Project 2007 Client.

After the changes are done by the team, when the project manager logs onto
the desktop client he is prompted to approve the updates. after the he
approves the client updates onto the server.

Later when i open the project from the server.. the changes are not visible
on the desktop client, but the changes are visible in PWA. How do i keep this
in sync??

Thanks
Bhanu Prasad
 
B

Bhanu Prasad

Ya cleared the local cache.. and opened up the file from project server.. the
changes are not reflecting. but when i llog on to the PWA its visible. the %
of work done is not getting updated.

another query.. sometimes few projects get into read-only mode. how do i get
it back to normal read-write state..

Thanks for help
 