Missing Tasks

B

Bdavis

Pardon me if I'm missing something obvious here: I have two projects
published to the server. Both are using the Enterprise Resource pool. For
project on 1, my taks are showing up in the 'My Tasks' section of PWA as well
as synching down to Outlook... works great. For Project #2, no suck luck, my
taks are visable at the project summary level bu they are not in the 'My
Tasks' list and they DO NOT sync down to outlook.

Any thoughts?
 
B

Ben Howard

Several...
1. My tasks by default shows current tasks, the value of which is set in
the server settings. ARe Project #2tasks outside the current task range.
2. In project 2, are you (the resource), the exact same enterprise resourse
in P1? - check the resource assignments page
3. Is the approval manager the same for P1 and P2

Please let us know the answers...
 
B

Bdavis

Let's
1) I can't find this parameter in Server Setting. Where is it located?
2) The resource (me) is definetly identical in both projects.
3) How do I check this?
 
B

Ben Howard

Hi
1. Server Settings | Task settings and display
2. I want to be really clear - d you see the assignements for both P1 and
P2 if you look for them in the resources page?
3. Insert the assignment owner column in project pro. Who is the
assignment owner in both P1 and P2 for the tasks that you are assigned to?
 