Naomin
If someone could please explain what "status" refers to I'd appreciate it.
To begin with, my project information shows Status NA. I've inserted the
status column and gotten the following:
The status on an unstarted task which is overude is, logically, "late".
However, when I put an actual start date on it, even though it's a late
start, the "start" column changes to the actual and the status changes to "on
schedule". Isn't this accomodating an incorrect situation? The baseline is
showing that that task is late!
thanks,
Naomi
To begin with, my project information shows Status NA. I've inserted the
status column and gotten the following:
The status on an unstarted task which is overude is, logically, "late".
However, when I put an actual start date on it, even though it's a late
start, the "start" column changes to the actual and the status changes to "on
schedule". Isn't this accomodating an incorrect situation? The baseline is
showing that that task is late!
thanks,
Naomi