Scott Morrissey
When our Project Managers Accept Actual hours into their plans, it changes
the Modified Date to the current date and time (like it is supposed to). They
rely on this date changing so they know which projects they need to
re-publish.
This has been working fine every week for over 2 months. Yesterday, however,
one project (and only 1 out of about 150 projects) successfully transfered
the hours into the plan - but it did NOT change the modified date. The Queue
shows that the status update was successful.
Does anyone know how this could have happened? Is there a known issue with
the modified date not getting changed? We are on the SP2 version.
the Modified Date to the current date and time (like it is supposed to). They
rely on this date changing so they know which projects they need to
re-publish.
This has been working fine every week for over 2 months. Yesterday, however,
one project (and only 1 out of about 150 projects) successfully transfered
the hours into the plan - but it did NOT change the modified date. The Queue
shows that the status update was successful.
Does anyone know how this could have happened? Is there a known issue with
the modified date not getting changed? We are on the SP2 version.