Modify resource calendars with non-working times.

C

C. Smith

We would like to modify the resource calendars with non-working times. I
tried to enter a vacation on a resource's calendar and got a message that all
calendars were locked. This is really an important function to be able to
show impacts of vacations.
Any insight?
 
R

Reid McTaggart

Did you open the Enterprise Resource Pool before trying to modify the
resource's calendar? Enterprise resources have to be "checked out" before
their personal calendars can be modified.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top