Modify the gantt chart view in project center (WPA) (MS Project 2010)

Joined
Apr 20, 2018
Messages
1
Reaction score
0
Hello

I would like to have a gantt view in WPA project center of the project with the :
- baseline summary bar (OK, done)
- Project summary (OK, done)
- Summary progress (OK, done)
(Please see the attach file)
=> But I didn't find the way to display the % of the summary progress (% completed). Could you help me please ?
(My boss wants to see the % of (duration) completion for the project)

Is it possible to :
- either define some text label to display in the "Gantt chart format" of WPA
- or is it possible to configure the gantt view of project center in MS project 2010 client with the text properties in the Bar styles windows ?
- Maybe I must change something in the enterprise global ??

I change some values in one of my 40 current projects on the MS Project client but it didn't publish the update in WPA.

I'm lost !!! Could you please give me some tips ?

One more question : Why when I'm am up to date in a project (no uncompleted task in the past) the summary progress is not fill in to the current date ? (On the picture, the 4th project is up to date but I have one week of "uncompleted work" and I don't understand why => I cannot justify the "delay" to my boss because the project is up to date :))

Thank for your help. I hope I was clear enough :)

Cedahlia
 

Attachments

  • CaptureMSPro.JPG
    CaptureMSPro.JPG
    29.5 KB · Views: 340

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top