S
Session
Hello,
Is it possible in MS Project to go back and re-baseline the cost (hourly
rate) of a resource without re-baselining the duration of the tasks? We
entered a wrong cost for one resource in the original baseline, and we want
to fix that for our earned value calculations, but we don't want to have the
baseline duration of tasks to be changed to the current plan (which is what
always happens when baselining). Is it possible? if so, how?
Thanks,
Session
Is it possible in MS Project to go back and re-baseline the cost (hourly
rate) of a resource without re-baselining the duration of the tasks? We
entered a wrong cost for one resource in the original baseline, and we want
to fix that for our earned value calculations, but we don't want to have the
baseline duration of tasks to be changed to the current plan (which is what
always happens when baselining). Is it possible? if so, how?
Thanks,
Session