Modifying the "Updates View" in Project Server

S

Seann

Is it possible to add fields to this view? Looking at the "Manage Views" in
the admin page it doesn't look like you can. I would like to add baselined
fields to this view so I can better see what values I'm accepting into my
project file.
 
D

Dale Howard [MVP]

Seann --

You can change the Updates page indirectly by adding the baseline fields to
the Timesheet view. Unlike the Timesheet view, however, you cannot set the
column order in the Updates page. Hope this helps.
 
S

Seann

Again Dale, you're the man. Thanks!

Dale Howard said:
Seann --

You can change the Updates page indirectly by adding the baseline fields to
the Timesheet view. Unlike the Timesheet view, however, you cannot set the
column order in the Updates page. Hope this helps.
 
D

Dale Howard [MVP]

Seann --

Thanks for the kind compliment! :) You are more than welcome for the help.
 