Franz12
Hi, I've set up a project 2007 containing several tasks with different
duration (or start and end dates). I've entered them as months or years, but
project always converts the duration to be displayed as days (which is not
feasible in our long term project). Furthermore, I used Visio 2007 to import
a project in a Gantt chart using the Gannt wizard. Works great, but
unfortunately, the duration is displayed in days again.... How to change it
to months or years in both project and visio gantt?? Thanks!! Franz
duration (or start and end dates). I've entered them as months or years, but
project always converts the duration to be displayed as days (which is not
feasible in our long term project). Furthermore, I used Visio 2007 to import
a project in a Gantt chart using the Gannt wizard. Works great, but
unfortunately, the duration is displayed in days again.... How to change it
to months or years in both project and visio gantt?? Thanks!! Franz