R
raduga_fb
Hi all,
I am trying to monitor the actual quantities. Civil works have "Resource
Name" (EX, LC, RC, BF) and their amount has been entered to "Units". In order
to this, "Resource Names" become "EX[367]".
Task Information -> "Excavation" -> Resources ->
Resource Name = EX
Units = 367
I update actual data to Number1 column as "Actual Quantity".
Task Number1 Number2 % Resource
Name Actual Qty Complete Names
-------------- ---------- ------- --------- --------
ZZZ Civil Construction 3%
Excavation 43 11 11% EX[367]
Lean Concrete 0 0 0% LC[10]
RCC of Footing 0 0 0% RC[189]
Backfilling 0 0 0% BF[168]
to get % Actual Complete automatically I created formula in Number2
Custom Fields -> Number 2 -> int([Number1]/Mid(([Resource
Names]),4,Len([Resource Names])-4)*100)
I can not apply same method to "% Complete". "% Complete" is standard column
in the microsoft project and can not be changed (at least I could not). I
have to update "% Complete" column manualy. Do I have another option ?
Number2 column does satisfied me. But I have to define additional formula
for main task "ZZZ Civil Construction" to calculate total percentage of work
(3%). Microsoft Project calculates it automatically in the "% Complete"
column.
Finally, How can I update / monitor "Actual Quantities" in easy way ? I
don`t want to use calculator to update "% Complete" column.
Regards,
I am trying to monitor the actual quantities. Civil works have "Resource
Name" (EX, LC, RC, BF) and their amount has been entered to "Units". In order
to this, "Resource Names" become "EX[367]".
Task Information -> "Excavation" -> Resources ->
Resource Name = EX
Units = 367
I update actual data to Number1 column as "Actual Quantity".
Task Number1 Number2 % Resource
Name Actual Qty Complete Names
-------------- ---------- ------- --------- --------
ZZZ Civil Construction 3%
Excavation 43 11 11% EX[367]
Lean Concrete 0 0 0% LC[10]
RCC of Footing 0 0 0% RC[189]
Backfilling 0 0 0% BF[168]
to get % Actual Complete automatically I created formula in Number2
Custom Fields -> Number 2 -> int([Number1]/Mid(([Resource
Names]),4,Len([Resource Names])-4)*100)
I can not apply same method to "% Complete". "% Complete" is standard column
in the microsoft project and can not be changed (at least I could not). I
have to update "% Complete" column manualy. Do I have another option ?
Number2 column does satisfied me. But I have to define additional formula
for main task "ZZZ Civil Construction" to calculate total percentage of work
(3%). Microsoft Project calculates it automatically in the "% Complete"
column.
Finally, How can I update / monitor "Actual Quantities" in easy way ? I
don`t want to use calculator to update "% Complete" column.
Regards,